Fitzgerald Creek, GA Case Study

Cherokee County Water and Sewerage Authority

Fitzgerald Creek, GA

Challenge

Cherokee County Water and Sewerage Authority (CCWSA) provides high quality water and sewer service to more than 170,000 residents in Cherokee County, GA. The CCWSA was established as a subdivision of the government of the State of Georgia by an act of the Georgia Legislature in 1955. CCWSA presently maintains and operates two wastewater facilities: Rose Creek and Fitzgerald Creek. A third plant, Riverbend, is due online this year.

Solution

CCWSA was already operating their own SCADA system. However, TDH offered an enticing alternative state-of-the-art solution: Sanitaire’s new customizable OSCAR process performance optimizer control system. For this project, Sanitaire would replace the existing programmable logic controller (PLC) and human machine interface (HMI) hardware and software to enable remote connectivity.

Download Case study